Late Stage Wetland Construction

These photos were taken 4/19 and 4/20 and show the final elevation of the constructed wetland.
   
 
The outlet side of the third dike. Here the two steel pipes and the two plastic, 'draw down' pipes are visable. The large steel pipes allow rapid flow-through after rain events and the perforated plastic pipes allow slow drainage down to a lower elevation. This way the wetland has a large, short-term capacity and a smaller long-term capacity.
 
The outlet side of the third dike. The lake is to the left of this photo.
The inlet side of the first dike.
Final elevation of the third cell.
Late in the excavation of the third cell.
 
These photos were taken 4/29, the afternoon after a storm went through that dropped .58" of rain.
The last cell accumulated just an inch or two of runoff
The second cell from a distance
The outlet of the second cell. This cell had filled to its capacity. The deepest point was ~18 inches.
Later Stage Wetland Construction